Update on Central Park

4-15 parking lot2

Work on Swarthmore’s Central Park project has moved ahead rapidly, recently including creation of a ramp connecting the parking level to the entrance of Borough Hall and the library. The parking lot will likely open next Tuesday or Wednesday (although final paving will wait until after the Fun-Fair on May 1), and construction work will be largely complete by the beginning of May.

Mayor Tim Kearney invites hale and hearty volunteers to take part in the creation of the project’s “rammed earth” bank on May 7-8, under the direction of artist/constructor Massey Burke — details to come in next week’s Swarthmorean.